For Dundalk Western Bypass, procured under a
PPP, we designed over 12km of dual carriageway plus 14 major
structures – and helped develop value engineering solutions in
critical areas such as bridge, drainage and pavement design
The objective of this high profile project was to complete the
motorway – around 12 km of dual carriageway and 14 principal
structures including the Ballynahattin Rail Bridge - between North
Dundalk in Co. Louth and Gormanstown in Co. Meath and to operate
and maintain it as a toll road. The project was procured by means
of a PPP (Public Private Partnership) contract.
The new-build section is a significant project in its own right,
with 1.25 million m
3 of earthworks as well as the 14
major structures The contractor identified the importance of
achieving the earliest completion possible which placed special
focus on design activities.
Designing for the upgrade of 42km of the existing M1 motorway,
included checking compliance with newly introduced standards,
represented a first for the National Road Network.
Value engineering played an important part in assisting the
contractor to investigate alternatives in critical areas such as
bridge design, drainage and pavement.
In the case of the underbridges, we helped the contractor by
examining a number of alternative options which offered advantages
as compared to the more traditional solutions. Selection of a
generic solution involving the use of reinforced earth abutments
and pre-cast beam decks resulted in significant programme savings.
Drainage design was optimised by considering a range of options
including kerb and gully solutions, concrete channel solutions and
grass channels. Alternative attenuation solutions were also
considered at outfall locations.
For the mainline pavements, CBM2 material was used as sub-base, to
an analysed design – the first use of this material in Ireland.
Ballynahattin Rail Bridge posed a major challenge to all involved
in the project. At 7,500 tonnes, this was the largest structure
ever constructed using the Autoripage method. We carried out all
the design work for the 40 degree skew bridge which was built off
line and moved 44m into place during the Easter weekend 2005,
resulting in the minimum curtailment of rail services between
Dublin and Belfast. The 83m long structure was slid into position
in a 72 hour possession period using the Autoripage technique. As
well as designing all the permanent works we also checked the
earthworks stability in the railway embankment.